Question 1403 - PMP discussion
One team member is complaining about an agreement made during the last meeting. That team member was present at the meeting and participated in the decisions registered in the meeting minutes.
What should the project manager do next?
A.
Schedule a new meeting to evaluate the agreement and negotiate a new one.
B.
Meet with the team member and search for the root cause of their behavior.
C.
Arrange an additional meeting with the team to communicate the agreement made during the last meeting.
D.
Talk with the team member and explain that once the meeting ended, the agreement must be respected.
Your answer: