Question 1404 - PMP discussion
Just as a team reaches a mutual consensus on a preferred design, a stakeholder submits a request to add new features that enhance the company's competitive advantage. What should the project manager do?
A.
Start the process to include the new features of the product on the next iteration.
B.
Allow all requested changes and bypass the company's change control process.
C.
Reject all requested changes and bypass the company's change control process.
D.
Encourage the project team to add premium features to impress the client.