A project manager has been appointed to lead a project but has not previously worked with the project team members. The project manager notices that the team is a mix of senior and junior professionals.

What should the project manager do to start establishing a successful relationship?

A.

Schedule one-on-one meetings with the project team members to coach them on how to do their work better based upon previous experience.

Answers
A.

Schedule one-on-one meetings with the project team members to coach them on how to do their work better based upon previous experience.

B.

Start speaking with each team member separately to understand their needs and personal goals to determine a leadership style.

Answers
B.

Start speaking with each team member separately to understand their needs and personal goals to determine a leadership style.

C.

Establish authority in the team by setting ground rules and key performance indicators (KPIs).

Answers
C.

Establish authority in the team by setting ground rules and key performance indicators (KPIs).

D.

Schedule a team-building activity and start meeting personally with the project team members.

Answers
D.

Schedule a team-building activity and start meeting personally with the project team members.

Suggested answer: D