During the initiation stage of a multimedia exhibition-design project, the project manager is developing the project management plan. What should the project manager do to complete this task?
A.
Initiate a survey to solicit end-customer opinions and prioritize exhibition contents.
B.
Initiate an additional services agreement in case the key deliverables list was not clearly stated in the contract.
C.
Benchmark other similar exhibitions' deliverable lists and final outcomes.
D.
Clarify the high-level business requirements with the event organizer as a basis for forming the deliverables list.