ExamGecko
Home Home / PMI / PMP
Question list
Search
Search

List of questions

Search

Related questions











Question 1270 - PMP discussion

Report
Export

A customer requests additional changes 1 day before the planned change date. How should the project manager respond to the change request?

A.

Reject the changes as the lead time is too short.

Answers
A.

Reject the changes as the lead time is too short.

B.

Check if the changes are covered in the statement of work (SOW).

Answers
B.

Check if the changes are covered in the statement of work (SOW).

C.

Determine whether the project team is capable of making the changes.

Answers
C.

Determine whether the project team is capable of making the changes.

D.

Review the additional changes and perform integrated change control.

Answers
D.

Review the additional changes and perform integrated change control.

Suggested answer: D
asked 12/11/2024
Frank Nwabueze
34 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first