Question 1270 - PMP discussion
A customer requests additional changes 1 day before the planned change date. How should the project manager respond to the change request?
A.
Reject the changes as the lead time is too short.
B.
Check if the changes are covered in the statement of work (SOW).
C.
Determine whether the project team is capable of making the changes.
D.
Review the additional changes and perform integrated change control.