A project manager implementing a hybrid project is dealing with multiple stakeholders in a rapidly changing business environment. How should the project manager ensure that the needs of stakeholders are consistently met?
A.
Add more iterative techniques to improve stakeholder learning.
B.
Use iterative life cycles involving stakeholders to enable the team to improve the product end result through successive prototypes.
C.
Identify all the critical stakeholders during project initiation.
D.
Assign one team member to one stakeholder to ensure that the responsible team member is conversant with the needs of the stakeholder.