A global petroleum crisis has affected the distribution of crude oil in the region where the construction project is underway. Materials are not being delivered on time and this phase of construction is already behind for what was initially planned.

What should the project manager do first to prevent the project from going further off track?

A.

Propose a pause in this phase to save labor costs and asset depreciation.

Answers
A.

Propose a pause in this phase to save labor costs and asset depreciation.

B.

Proceed with the project using management reserves to cover any delays or losses.

Answers
B.

Proceed with the project using management reserves to cover any delays or losses.

C.

Establish new partnerships with other suppliers in anticipation of any delays.

Answers
C.

Establish new partnerships with other suppliers in anticipation of any delays.

D.

Perform a risk assessment and define a risk response action plan.

Answers
D.

Perform a risk assessment and define a risk response action plan.

Suggested answer: D