ExamGecko
Home Home / PMI / PMP
Question list
Search
Search

List of questions

Search

Related questions











Question 1295 - PMP discussion

Report
Export

After a project team has been working on a project for several months, the project is cancelled.

The project sponsor is putting pressure on the project manager to perform closeout duties as fast as possible so that the project team can move on to other work. The project sponsor has instructed the team not to waste time archiving the project artifacts for the cancelled project.

How should the project manager handle this situation?

A.

Archive the project artifacts on the project manager's local computer for future reference.

Answers
A.

Archive the project artifacts on the project manager's local computer for future reference.

B.

Document the project sponsor's instructions as the archived project artifacts.

Answers
B.

Document the project sponsor's instructions as the archived project artifacts.

C.

Comply with the project sponsor's request to not archive the project artifacts.

Answers
C.

Comply with the project sponsor's request to not archive the project artifacts.

D.

Consult with the project management office (PMO) for guidance on project artifacts.

Answers
D.

Consult with the project management office (PMO) for guidance on project artifacts.

Suggested answer: D
asked 12/11/2024
Rannie Dayapan
42 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first