ExamGecko
Home Home / PMI / PMP
Question list
Search
Search

List of questions

Search

Related questions











Question 1300 - PMP discussion

Report
Export

A project manager created a contingency plan associated with a risk. The risk was realized, but the client insists on using a new workaround instead. The requested workaround will introduce delays and require additional budget.

What should the project manager do?

A.

Request to use the management reserve to keep the schedule.

Answers
A.

Request to use the management reserve to keep the schedule.

B.

Discuss the options with the client as part of the change control process.

Answers
B.

Discuss the options with the client as part of the change control process.

C.

Proceed with the approved risk response plan.

Answers
C.

Proceed with the approved risk response plan.

D.

Mitigate risks associated with the workaround to avoid project delays.

Answers
D.

Mitigate risks associated with the workaround to avoid project delays.

Suggested answer: B
asked 12/11/2024
mahdis khaledi
46 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first