Question 1304 - PMP discussion

Report
Export

A project manager is leading a project that is at 90% completion. One of the key stakeholders requests a certification program to be included as part of the project. Another stakeholder disagrees and informs the project team that there should be no change to the project management plan since the project is nearing completion.

What should the project manager do?

A.

Raise a change request to the change control board (CCB) and inform the project sponsor about the change.

Answers
A.

Raise a change request to the change control board (CCB) and inform the project sponsor about the change.

B.

Update the project management plan and adjust the project budget with this change request.

Answers
B.

Update the project management plan and adjust the project budget with this change request.

C.

Ask the key stakeholder to take the lead in handling the request since they are more knowledgeable.

Answers
C.

Ask the key stakeholder to take the lead in handling the request since they are more knowledgeable.

D.

Request a meeting with the stakeholders and their team members to inform them about this change.

Answers
D.

Request a meeting with the stakeholders and their team members to inform them about this change.

Suggested answer: A