A human resources (HR) cost report was disclosed, by error, to all members of the project team.

This situation generated a conflict between the team members about differences in their salaries.

What should the project manager have done to avoid this situation?

A.

Ensured reports with significant information were not included in the communications management plan

Answers
A.

Ensured reports with significant information were not included in the communications management plan

B.

Included noncompliance punishment measures in the communications management plan

Answers
B.

Included noncompliance punishment measures in the communications management plan

C.

Defined the appropriate recipients for the report in the communications management plan

Answers
C.

Defined the appropriate recipients for the report in the communications management plan

D.

Validated the information and the appropriate recipients per the communications management plan

Answers
D.

Validated the information and the appropriate recipients per the communications management plan

Suggested answer: D