A project manager is nearing completion of an automation project. One of the key stakeholders requests a meeting to discuss some new ideas that would make the project even more appealing to end users. As a result, the stakeholder suggests that the project manager does not close the project.

What should the project manager do first?

A.

Add it to the issue log as an ongoing issue.

Answers
A.

Add it to the issue log as an ongoing issue.

B.

Review and validate the scope management plan.

Answers
B.

Review and validate the scope management plan.

C.

Update the project charter with the new requirement.

Answers
C.

Update the project charter with the new requirement.

D.

Add a risk to the risk register.

Answers
D.

Add a risk to the risk register.

Suggested answer: B