This graph describes the current performance of a project in relation to cost and schedule. What should the project manager do to bring the project back on track?
A.
Review project schedule because the project is under budget and behind schedule.
B.
Review project scope because the project is under budget and ahead of schedule.
C.
Review project schedule and cost because the project is over budget and behind schedule.
D.
Review project cost because the project is over budget and ahead of schedule.