Question 1348 - PMP discussion
A project manager is assigned to a large construction project with more than 100 project team members. The project manager is having a hard time keeping the project on track and deriving the planned benefits. The project manager wants to make sure that each requirement is linked to the business and project objective.
What should the project manager do?
A.
Understand the project management plan.
B.
Review the requirements on a weekly basis.
C.
Implement a requirements traceability matrix.
D.
Add the requirements to the project charter.
Your answer: