During a meeting to define project scope a stakeholder tells the project manager that the main requested feature in the contract is not applicable, and this is documented in the lessons learned.

What should the project manager do?

A.

Ask the sponsor to close the project and pay the contracted penalty.

Answers
A.

Ask the sponsor to close the project and pay the contracted penalty.

B.

Meet with the sponsor to ask for their support.

Answers
B.

Meet with the sponsor to ask for their support.

C.

Check with the team to learn what can be done, and consult an expert.

Answers
C.

Check with the team to learn what can be done, and consult an expert.

D.

Check that this information was documented correctly.

Answers
D.

Check that this information was documented correctly.

Suggested answer: D