Question 1367 - PMP discussion

Report
Export

A project team member informs the project manager that a stakeholder is contacting the team member to request status updates. The team member is being distracted by these repeated requests, which are interfering with the completion of assigned tasks.

What should the project manager do?

A.

Review this stakeholder's communication requirements.

Answers
A.

Review this stakeholder's communication requirements.

B.

Inform the team member to stop sending any further updates to the stakeholder.

Answers
B.

Inform the team member to stop sending any further updates to the stakeholder.

C.

Increase the frequency of updates given to this stakeholder.

Answers
C.

Increase the frequency of updates given to this stakeholder.

D.

Raise this issue to the project sponsor in the next project status review meeting.

Answers
D.

Raise this issue to the project sponsor in the next project status review meeting.

Suggested answer: A