Question 1380 - PMP discussion
Within a project, senior management is requesting project information so they can analyze the data to make project decisions. What information should the project manager provide so that senior management can get a broader view of the project?
A.
Higher-level activities completed
B.
Milestones status report
C.
Risk register information
D.
Resource breakdown structure (RBS)