List of questions
Related questions
Question 1385 - PMP discussion
A project manager has been assigned to a project that is consolidating regional operations into a global operation. The project sponsor explains that some efficiencies could be obtained from this unification.
However, the sponsor is not sure if this effort will have a return on investment (ROI) and would like the project manager's opinion.
What should the project manager do?
Request the project sponsor to include a commitment from the stakeholders to reduce costs within the project scope.
Suggest conducting a detailed cost-benefit analysis for financial feasibility before the start of the project.
Recommend conducting an initial high-level feasibility assessment to estimate the cost and benefits.
Explain that the project manager is limited to demonstrating earned value (EV) from the project execution perspective.
0 comments
Leave a comment first