ExamGecko
Home Home / PMI / PMP
Question list
Search
Search

List of questions

Search

Related questions











Question 1385 - PMP discussion

Report
Export

A project manager has been assigned to a project that is consolidating regional operations into a global operation. The project sponsor explains that some efficiencies could be obtained from this unification.

However, the sponsor is not sure if this effort will have a return on investment (ROI) and would like the project manager's opinion.

What should the project manager do?

A.

Request the project sponsor to include a commitment from the stakeholders to reduce costs within the project scope.

Answers
A.

Request the project sponsor to include a commitment from the stakeholders to reduce costs within the project scope.

B.

Suggest conducting a detailed cost-benefit analysis for financial feasibility before the start of the project.

Answers
B.

Suggest conducting a detailed cost-benefit analysis for financial feasibility before the start of the project.

C.

Recommend conducting an initial high-level feasibility assessment to estimate the cost and benefits.

Answers
C.

Recommend conducting an initial high-level feasibility assessment to estimate the cost and benefits.

D.

Explain that the project manager is limited to demonstrating earned value (EV) from the project execution perspective.

Answers
D.

Explain that the project manager is limited to demonstrating earned value (EV) from the project execution perspective.

Suggested answer: B
asked 12/11/2024
Ronald DeCastro
32 questions
User
Your answer:
0 comments
Sorted by

Leave a comment first