Question 1388 - PMP discussion

Report
Export

A team is testing a product on multiple radio frequencies. The project manager is informed that a new government policy, expected in 2 weeks, will mandate companies to obtain approval and licensing for frequency testing. The team has completed 80% of the testing and needs 4 weeks to complete the remaining tests.

Which two actions should the project manager take until the approval is received? (Choose two.)

A.

Hire a vendor with the required expertise and infrastructure to complete the testing.

Answers
A.

Hire a vendor with the required expertise and infrastructure to complete the testing.

B.

Stop testing immediately and escalate the issue to senior management for a decision.

Answers
B.

Stop testing immediately and escalate the issue to senior management for a decision.

C.

Allow testing to continue for the complete duration as the policy may not apply to ongoing projects.

Answers
C.

Allow testing to continue for the complete duration as the policy may not apply to ongoing projects.

D.

Update the project risk checklist to consider licensing and approvals for risk identification.

Answers
D.

Update the project risk checklist to consider licensing and approvals for risk identification.

E.

Reallocate the testing resources to complete testing early before the policy takes effect.

Answers
E.

Reallocate the testing resources to complete testing early before the policy takes effect.

Suggested answer: D, E