During a meeting with project stakeholders, a stakeholder who is known for causing problems, questions the project manager's authority to implement new processes for functional managers.

What should the project manager do?

A.

Refer to the change management plan and review the documented process changes.

Answers
A.

Refer to the change management plan and review the documented process changes.

B.

Meet with the stakeholder individually.

Answers
B.

Meet with the stakeholder individually.

C.

Refer the stakeholder to the approved project charter.

Answers
C.

Refer the stakeholder to the approved project charter.

D.

Explain that the potential risks will be addressed in the risk management plan.

Answers
D.

Explain that the potential risks will be addressed in the risk management plan.

Suggested answer: C