A project manager is working on a product development project. When the product is delivered, there are major issues that require rework and delay new feature development.

Which action should the project manager take to resolve the quality issues?

A.

Discuss adding business scenario tests with the customer.

Answers
A.

Discuss adding business scenario tests with the customer.

B.

Discuss adding additional test cases with the product owner.

Answers
B.

Discuss adding additional test cases with the product owner.

C.

Add more test scenarios based on the issues found.

Answers
C.

Add more test scenarios based on the issues found.

D.

Plan for continuous validation of the product.

Answers
D.

Plan for continuous validation of the product.

Suggested answer: D