Question 1422 - PMP discussion
During the last two iterations of a project, one of the team members had low performance. The project manager conducted two feedback sessions with the team member and escalated the issue to the resource manager and project sponsor, but there has been no improvement.
What should the project manager do next?
A.
Request a new resource to execute the activities.
B.
Review this obstacle during the daily standup meeting.
C.
Escalate the situation again to the project sponsor.
D.
Provide feedback to the resource at the sprint review.
Your answer: