Question 1425 - PMP discussion
The customer wants to show their stakeholders a tangible outcome faster. This requires advancing a milestone.
Which two actions should the project manager do? (Choose two.)
A.
Review the customer's priorities regarding the desired requirements for the milestones.
B.
Convince the customer to keep the requirements as is and not move the milestone.
C.
Discuss which requirements can be delivered faster with the project team.
D.
Inform the customer that moving the milestone has a very high impact on project cost.
E.
Escalate the issue to senior management so they can impose a solution on the customer.