The project manager is reviewing the program risks and issues with key stakeholders. One of the stakeholders wants to understand when the risk may potentially become an issue.

What artifact should the project manager share with the stakeholder?

A.

Project management plan

Answers
A.

Project management plan

B.

Issue log

Answers
B.

Issue log

C.

Risk management plan

Answers
C.

Risk management plan

D.

Risk register

Answers
D.

Risk register

Suggested answer: D