Question 1444 - PMP discussion
A project manager is working on the implementation of new phases in the production process of a regulated industry. Which two stakeholders can help the project manager determine and address compliance requirements? (Choose two.)
A.
Risk steering committee
B.
Chief executive officer
C.
Functional managers
D.
Board of directors
E.
Advisory team panel
Your answer: