List of questions
Related questions
Question 1453 - PMP discussion
Due to unforeseen circumstances, a contractor was unable to mobilize the project team, which was necessary to conduct face-to-face meetings and discussions. Virtual meetings were subsequently put in place, but the local project team and end users now face a communication gap that is causing the team's low performance.
What should the project manager do?
A.
Ask the contractor to solve this problem because this is a contractual obligation.
B.
Terminate the contract and initiate a new one with a local contractor.
C.
Reassess continually to remove blockers for the team.
D.
Implement key performance indicators (KPIs) and convince the contractor to engage the team.
Your answer:
0 comments
Sorted by
Leave a comment first