During a team meeting the new agile project manager becomes aware that there are many complaints from the customer regarding project stability and other critical issues. A team member states that the deliverables were developed by experienced employees who confirmed that the project was stable.
How should the new project manager address these concerns?
A.
Allow the agile team to decide what they are able to deliver in each iteration
B.
Ask the team for additional feedback and add tasks to the task board
C.
Document the customer's complaints and critical issues in the issue log
D.
Hold a brainstorming session to identify the root cause of the complaints