List of questions
Related questions
Question 1476 - PMP discussion
A project team member raised a risk that the threat of country-wide power cuts may affect the project time line for a software development project. In the last month, this risk materialized and the project time line had to be extended by 2 months.
Which two actions should the project manager take? (Choose two.)
Ask the team member to work overtime to make up the lime lost so that the project schedule is not impacted.
Log it in the risk register and work with the relevant owner to implement the mitigation action plan.
Analyze the impact of the issue and submit a change request to update the project schedule.
Inform the project sponsor that the risk has materialized and request that the project budget be increased.
Extend the project deadline and update the project schedule to reflect the delay.
0 comments
Leave a comment first