Question 162 - PMI-ACP discussion
Team A is working on the second sprint of a product release Team B. which is an interdependent team located on the same floor requires extensive and frequent information to complete its sprint goal What should the agile team lead do?
A.
Create a central repository for information, and provide access to team B
B.
Use an information board that will be visible to an passing through the workspace
C.
Email ail stakeholders with status updates
D.
Provide team B with the information on an "as needed" basis
Your answer: