Question 205 - PMI-ACP discussion
A newly formed development learn experienced difficulty with accurately estimating product backlog items As a result, the team failed to deliver all of the features in the sprint backlog for the past two iterations What should the team do to improve the accuracy of their estimates?
A.
Decrease the sprint time box until the team is able to deliver the entire agreed-upon sprint backlog tn a single sprint
B.
Discuss estimating techniques in the daily scrum meeting
C.
Increase the size of the development team until the team is able to deliver the entire agreed-upon sprint backlog in a single sprint
D.
Begin tracking estimated effort metrics as an input to performance evaluation.