Question 12 - PMP discussion
A project manager wants to make sure that similar projects in the future use the project's performance data as a reference. However, the project manager is not sure how to accomplish this.
What should the project manager do?
A.
Keep project artifacts up-to-date and accessible to all stakeholders
B.
Share project documentation in a repository with exclusive access
C.
Schedule weekly knowledge-sharing sessions with key stakeholders
D.
Send periodic emails to senior management with the latest project updates