A project manager is leading a multiyear project that involves internal and external stakeholders.

As the project manager begins to gather requirements, additional business stakeholders express interest in being involved.

Which three actions should the project manager take to ensure proper stakeholder involvement?

(Choose three.)

A.
Prioritize stakeholders based on the project phase and need
Answers
A.
Prioritize stakeholders based on the project phase and need
B.
Perform a stakeholder assessment to align with the project objectives
Answers
B.
Perform a stakeholder assessment to align with the project objectives
C.
Classify and rank stakeholders based on their positions in the organization
Answers
C.
Classify and rank stakeholders based on their positions in the organization
D.
Include all stakeholders in the stakeholder engagement plan and provide the same level of communication
Answers
D.
Include all stakeholders in the stakeholder engagement plan and provide the same level of communication
E.
Develop a stakeholder impact/influence matrix to determine the level of engagement
Answers
E.
Develop a stakeholder impact/influence matrix to determine the level of engagement
Suggested answer: A, B, E