A project manager is overseeing a project as part of a program geared toward a major technology disruption. The team is comprised of brilliant young professionals who have worked on different projects for the organization in the past.

However, the team complained that they previously experienced a lack of direction during project execution and are afraid of the same issue in this project.

Which two actions should the project manager take to ensure that this issue does not occur in this project? (Choose two.)

A.
Organize a team-bonding activity and invite an external manager to speak to the team.
Answers
A.
Organize a team-bonding activity and invite an external manager to speak to the team.
B.
Set a clear vision for the project and ensure it is visible to all stakeholders.
Answers
B.
Set a clear vision for the project and ensure it is visible to all stakeholders.
C.
Focus on the resource management plan and track project progress.
Answers
C.
Focus on the resource management plan and track project progress.
D.
Encourage the team to do a brainstorming session and provide a mitigation plan.
Answers
D.
Encourage the team to do a brainstorming session and provide a mitigation plan.
E.
Keep the team engaged and focused on the project's direction.
Answers
E.
Keep the team engaged and focused on the project's direction.
Suggested answer: B, E