Question 38 - PMP discussion
A newly formed project team includes team members who have been working in the company for a long time as well as team members who are new to the company. The project team members discovered that there is a gap in communication between these two groups, and they are finding it hard to collaborate with one another.
What should the project manager do?
A.
Ask the experienced members to lead the junior members to facilitate skill transfer
B.
Organize networking sessions to allow the team members to get to know one another
C.
Encourage team members to focus on delivering results with their specialized skills
D.
Ask the team to self-organize and escalate any issues to the project manager
Your answer: