A regulatory branch of an environmental government agency has recently placed a ban on the manufacturing of a specified thickness of plastic packaging products. This ban will take effect in 12 months. The project manager for a startup firm working in alternative packaging has been monitoring the progress of this law for a while and, as part of the risk management, has identified new products that can support a growing customer base.

What should the project manager do next?

A.
Begin a marketing campaign to sell alternative packaging after the 12-month period ends
Answers
A.
Begin a marketing campaign to sell alternative packaging after the 12-month period ends
B.
Organize a meeting with all stakeholders and review the stakeholder engagement plan
Answers
B.
Organize a meeting with all stakeholders and review the stakeholder engagement plan
C.
Continue production processes and plan to discuss changes at the next annual target review meeting
Answers
C.
Continue production processes and plan to discuss changes at the next annual target review meeting
D.
Inform management of the new law as an opportunity to expand market share and share the proposed products
Answers
D.
Inform management of the new law as an opportunity to expand market share and share the proposed products
Suggested answer: D