Question 61 - PMP discussion
A project manager has just been hired by a company without a project management governance structure. During the kick-off meeting, a key stakeholder emphasizes the importance of the project meeting the company's strategy, investment, and compliance requirements.
What should the project manager do?
A.
Put into place a project governance model in line with the requirements
B.
Replicate the organizational governance to the project governance
C.
Create an organizational project management governance
D.
Ask the organization to create a project portfolio governance