A project manager is part of a global project team and is in charge of managing the scope defined by their country. There is a clear division regarding which pieces of the scope should be treated by global and local teams. During the last sprints, the project manager has been receiving requests that the global team should handle.

What should the project manager do in this situation?

A.
Assess the team's capacity to absorb the workload
Answers
A.
Assess the team's capacity to absorb the workload
B.
Evaluate and understand the cause of the conflict
Answers
B.
Evaluate and understand the cause of the conflict
C.
Escalate the situation to the project sponsor
Answers
C.
Escalate the situation to the project sponsor
D.
Reject the workload back to the global team
Answers
D.
Reject the workload back to the global team
Suggested answer: A