Question 94 - PMP discussion

Report
Export

A project manager for a technologically complex engagement reviews the key project indicators with the main stakeholders on a regular basis. During one of the meetings, the project sponsor explains that they are using the project manager's risk register as a way to communicate about the project at the executive level.

How should the project manager ensure that project risks are reported accurately in the risk register?

A.
Update the risks in the risk management plan
Answers
A.
Update the risks in the risk management plan
B.
Review the risks throughout project execution
Answers
B.
Review the risks throughout project execution
C.
List the project risks identified in the kick-off meeting
Answers
C.
List the project risks identified in the kick-off meeting
D.
Plan to update the risks at project closure
Answers
D.
Plan to update the risks at project closure
Suggested answer: B