Question 96 - PMP discussion
A project manager sent the first communication about the project management plan to the team.
The next day, two field engineers were asking about their roles and the project schedule.
What should the project manager have done?
A.
Sent the roles and responsibilities matrix along with the project management plan
B.
Confirmed that the communication was understood and solicited feedback from the team
C.
Briefed each team member on their roles before sending the project management plan
D.
Discussed the roles with the managers to help explain them to their team members