A project manager is managing a very important business transformation project. The goal of the project is to extend a desktop application with a mobile application module. The marketing department believes that a main competitor is working on a similar product.
Which delivery approach should the project manager use for this project?
A.
Extreme Programming (XP) delivery, to mitigate the high risk related to a new product
B.
Traditional delivery, to ensure high quality and that the product meets market demands
C.
Incremental delivery, to ensure that mobile capability is released fast to the users
D.
Iterative delivery, to ensure that user feedback is incorporated into the second iteration
Your answer: