A company that uses a predictive approach and operates in a highly regulated market is losing profitability because its product life cycle is taking longer than those of its competitors. A new project manager has been hired to change this scenario.

What approach should the project manager propose?

A.
Migrate to an agile model, focusing primarily on an iterative approach, leaving the incremental life cycle as a next step
Answers
A.
Migrate to an agile model, focusing primarily on an iterative approach, leaving the incremental life cycle as a next step
B.
Change to an agile model, focusing primarily on the incremental life cycle, leaving the iterative approach as a next step
Answers
B.
Change to an agile model, focusing primarily on the incremental life cycle, leaving the iterative approach as a next step
C.
Maintain a predictive approach, but increase the focus on better planning and tracking to anticipate problems and avoid delays
Answers
C.
Maintain a predictive approach, but increase the focus on better planning and tracking to anticipate problems and avoid delays
D.
Propose a hybrid approach, leveraging the benefits of an agile approach while respecting some aspects of the company's industry
Answers
D.
Propose a hybrid approach, leveraging the benefits of an agile approach while respecting some aspects of the company's industry
Suggested answer: D