The scope of a project is to replace the street signs within a 10-km radius. The client does not want to sign the project closure report if the radius is not extended by 1 km, to be aligned with the council's development plan.
What should the project manager do?
A.
Delay the approval and ask the project sponsor for additional funding.
B.
Contact the council and ask for their approval to extend the scope of the project.
C.
Initiate a new project and discuss the request because it came in too late.
D.
Obtain formal acceptance for the completed work and submit a change request.