Question 127 - PMP discussion
A project manager is in a cross-functional agile team. The project manager has been assigned a software project with multiple features that will take the team about a year to complete. The CEO is insisting that the solution needs to meet business goals for the year end, which is due in 6 months.
What should the project manager do to align stakeholders' needs and expectations?
A.
Work with the stakeholders to create a prioritized backlog and release a roadmap.
B.
Modify the requirements to those that can be completed in 6 months.
C.
Implement fast-tracking and crashing activities to complete the project in 6 months.
D.
Include all stakeholders in daily scrum meetings to keep them informed.