List of questions
Related questions
Question 135 - PMP discussion
A project is about to start. The project manager has found that the client does not have an appropriate knowledge management system and does not have a requirement for it.
What should the project manager do?
A.
Provide just-in-time knowledge to the client, upon request.
B.
Utilize the cloud wiki to collect the necessary knowledge.
C.
Ask the team to collect the knowledge locally and share it at the end of the project.
D.
Coordinate with the team and the project stakeholders to collect the knowledge.
Your answer:
0 comments
Sorted by
Leave a comment first