When a project is in its final stage, the project manager will request from the team to prepare a delivery acceptance document.

What is the importance of this document to the project manager?

A.
Needed to close the work breakdown structure (WBS).
Answers
A.
Needed to close the work breakdown structure (WBS).
B.
Needed to share it with the stakeholders.
Answers
B.
Needed to share it with the stakeholders.
C.
Needed to close out the project or a phase.
Answers
C.
Needed to close out the project or a phase.
D.
Needed to release the team at the end of the project.
Answers
D.
Needed to release the team at the end of the project.
Suggested answer: C