A facility extension project is in the execution stage. There is a project activity to connect the power of all new equipment to an existing facility, Point A, which requires a significant cable length. The construction team found that the power could be connected to Point B and save money.
What should the project manager do next?
A.
Perform a cost-benefit analysis to evaluate using the Point B option.
B.
Add the issue to the change log and request additional budget through the change control board (CCB).
C.
Seek a decision from the construction team after explaining the project budget and schedule constraint.
D.
Use the Point B option because it will save the project cost and time.
Your answer: