A facility extension project is in the execution stage. There is a project activity to connect the power of all new equipment to an existing facility, Point A, which requires a significant cable length. The construction team found that the power could be connected to Point B and save money.

What should the project manager do next?

A.
Perform a cost-benefit analysis to evaluate using the Point B option.
Answers
A.
Perform a cost-benefit analysis to evaluate using the Point B option.
B.
Add the issue to the change log and request additional budget through the change control board (CCB).
Answers
B.
Add the issue to the change log and request additional budget through the change control board (CCB).
C.
Seek a decision from the construction team after explaining the project budget and schedule constraint.
Answers
C.
Seek a decision from the construction team after explaining the project budget and schedule constraint.
D.
Use the Point B option because it will save the project cost and time.
Answers
D.
Use the Point B option because it will save the project cost and time.
Suggested answer: A