Question 184 - PMP discussion
In a financial company, a strategic project has been planned to use a predictive approach. During project planning, the product leader requests that milestones be submitted for review. There is a defined scope and an established deadline to conclude the project.
What should the project manager do first to meet the product leader's expectations?
A.
Change the project charter to indicate that the approach will be different.
B.
Inform the product leader that they must wait until the end of the project.
C.
Meet with the software team to review the possibility of monthly milestone reviews.
D.
Modify the project management plan to use an agile framework to incorporate milestones.