Question 186 - PMP discussion
A project manager received a request to add features and functions to the project after the scope had already been established.
What should the project manager do?
A.
Follow the requirements management process.
B.
Follow the stakeholder engagement process.
C.
Follow the risk management process.
D.
Follow the change management process.
Your answer: