A project team was hired to perform on-site duties, but there were unexpected circumstances that required the entire team to work remotely. Some team members returned to their hometowns, and they are now requesting reimbursement for operational expenditures.

What should the project manager do?

A.
Review the budget and allocate funds for the reimbursements.
Answers
A.
Review the budget and allocate funds for the reimbursements.
B.
Update the project management plan with the incurred costs.
Answers
B.
Update the project management plan with the incurred costs.
C.
Ask the team members to draft a justification before processing the reimbursements.
Answers
C.
Ask the team members to draft a justification before processing the reimbursements.
D.
Follow the Perform Integrated Change Control process and submit a change request.
Answers
D.
Follow the Perform Integrated Change Control process and submit a change request.
Suggested answer: D