In the daily check-in meeting, a team member informs the project team that the licenses for one of the components that will be used will expire in a couple of months. The licensing cost is significant.

What should the project manager do next?

A.
Evaluate the impact of nonrenewal of the license.
Answers
A.
Evaluate the impact of nonrenewal of the license.
B.
Escalate the licensing issue to the product owner.
Answers
B.
Escalate the licensing issue to the product owner.
C.
Add a spike to the backlog for an alternative design.
Answers
C.
Add a spike to the backlog for an alternative design.
D.
Raise a change request to secure the renewal.
Answers
D.
Raise a change request to secure the renewal.
Suggested answer: A